News Release Date
05-05-2026
Please be advised that Phase 2 of the Old Highway 99 Overlay Project begins May 18, 2026. This word goes from Miles Sand and Gravel west to the Tenino City Limits. Work will be done at night for minimal impact to commuters.
The proposed timeline is as follows:
Traffic Control Setup: 5/18/2026
HMA Planing: 5/19/2026
HMA Paving: 5/20/2026- 5/21/2026
Shoulder Rock: 5/26/2026
Centerline Rumble Strip: 5/27/2026
Striping and Recessed Pavement Markings: 6/10/2026